A 100-Megawatt Project Opens a New Path to Address the Electricity Crisis in Wadi Hadramout

The city of Seiyun witnessed on Wednesday, April 15, 2026, the laying of the foundation stone for a project to build two emergency electricity generation plants with a combined capacity of 100 megawatts, split between Al-Ghurf in Tarim District, with a capacity of 60 megawatts, and Badrah in Wadi Al Ayn and Hawrah District, with a capacity of 40 megawatts. The project is funded by Saudi Arabia and aims to reduce the electricity deficit and improve service stability in the districts of the valley and desert.

Sayun, The Valley and Desert The foundation-stone-laying ceremony was held in the city of Seiyun, while the project is distributed across two separate sites in Al-Ghurf and Badrah. The Electricity Crisis in Hadramout

Wadi Hadramout’s electricity file entered a new phase on Wednesday, April 15, 2026, with the official announcement of the start of implementation of a project to build two emergency electricity generation plants with a total capacity of up to 100 megawatts. The step aims to boost the generation capacity of a system that has faced recurring deficits and increased hours of power outages for years.

The foundation-stone-laying ceremony was held in the city of Seiyun, in the presence of officials from the local authority, the Public Electricity Corporation, and representatives of the Saudi Program for Development and Reconstruction of Yemen, as part of efforts to expand generation capacity and provide new solutions to meet growing energy demand.

The project includes the construction of two power plants at separate sites in Wadi Hadramout: the first in the Al-Ghurf area of Tarim District, with a planned generation capacity of 60 megawatts, and the second in the Badrah area of Wadi Al Ayn and Hawrah District, with a capacity of 40 megawatts.

The project’s distribution between the two sites is part of a plan to strengthen generation capacity in the valley’s system, enabling new generation sources to be added after construction and technical work is completed and the two plants are connected to the electricity grid.

The project is funded by the Saudi Program for Development and Reconstruction of Yemen, supervised by the Ministry of Electricity and Energy, and implemented by Gulf International Energy Company, according to the Public Electricity Corporation in the Wadi Hadramout region.

The announcement came amid the ongoing challenges facing the valley’s electricity system, foremost among them the gap between demand and generated power, as well as technical faults and fuel shortages that in previous years caused generation units to stop operating and outages to increase.

During the foundation-stone-laying ceremony, Hadramout Governor’s Deputy for the Valley and Desert Districts, Jumaan Salmeen Barba’a, stressed the importance of completing the project according to the specified timetable, describing it as one of the anticipated measures to improve service and ease residents’ hardship, particularly during peak summer periods.

The event was attended by Deputy Governor Engineer Hisham Al-Saidi, Director General of the Public Electricity Corporation in Wadi Hadramout Dr. Khaled Bahreish, representatives of the Saudi Program for Development and Reconstruction of Yemen, as well as local officials and technicians from the relevant entities.

The Director General of Valley Electricity explained that the project aims to support the system with additional capacity at the Al-Ghurf and Badrah sites, helping, once operational, to reduce the deficit and outage hours and improve electricity supply to the areas served.

The project is part of a broader drive to strengthen electricity infrastructure in Hadramout. On April 13, a foundation-stone-laying ceremony was held for a project to build two emergency power plants on the governorate’s coast, with a similar total capacity of 100 megawatts, divided between Joul Mas’hah and Ambykhah.

This means that the announced projects for the coast and the valley aim to add a planned total capacity of 200 megawatts across the governorate, at 100 megawatts for each area, with different implementation sites and electricity systems to be served.

The selection of Al-Ghurf and Badrah as sites for the two plants is operationally significant, given their links to areas within the valley’s electricity grid. The new capacity is expected to help boost power generation and ease pressure on existing plants once the project is completed and enters operation.

Nevertheless, the laying of the foundation stone marks the start of the announced implementation process; it does not mean that the two plants have entered service or that the full 100-megawatt capacity has been added to actual generation on the day of the announcement.

The project’s expected impact also depends on completing construction, installing generation units, securing operational requirements, completing grid-connection work, and ensuring regular maintenance and the resources needed to sustain production.

This development marks an important shift in the nature of measures related to the electricity crisis in Wadi Hadramout. After years of emergency responses to faults, fuel shortages, and generator stoppages, the announced efforts have turned toward adding new generation capacity that could help reduce the deficit more sustainably.

The event of April 15, 2026, holds particular significance in the chronological record of Hadramout’s electricity crisis, as a milestone documenting the launch of a project to expand generation capacity and opening the way to follow its subsequent implementation stages, through to actual operation and assessment of its impact on electricity supply hours.

The project’s success remains contingent on turning the announced plans into actual generation capacity reaching consumers, making the monitoring of implementation, completion dates, and start of operations an essential part of ongoing journalistic documentation of this issue.

Sources

1
Official source وضع حجر أساس مشروع محطات الكهرباء الإسعافية بقدرة 100 ميقا وات بوادي حضرموت — إعلام كهرباء وادي حضرموت (accessed 2026-10-18)