Sudden Fault at PetroMasila Station Restores Power Outages in Wadi Hadramout Days After Its Opening
The electricity system in Wadi Hadramout suffered an operational setback days after the opening of the PetroMasila gas-fired station, after a technical fault affected the gas compressor and shut down one of the turbines. This increased the electricity deficit and doubled daily outage periods, prompting an official apology from the Electricity Corporation to citizens.
The electricity sector in Wadi Hadramout experienced a new service disruption in early May 2018, after a technical fault occurred in the gas pressure system at the PetroMasila gas-fired station. The fault led to the shutdown of one of the generating turbines and a decline in the capacity available to the electricity grid, just days after the station’s official opening with a design capacity of 75 megawatts.
The General Electricity Corporation in the Wadi Hadramout area disclosed, in a statement published on Tuesday, May 1, 2018, that the fault affected the gas compressor, technically known as “GAS COMPRESSOR,” one of the components involved in supplying the gas needed to operate the generating units.
The fault took one of the station’s turbines out of service, increasing the shortfall between generated power and electricity demand and prompting the corporation to revise the outage schedule in the districts of the valley and desert.
According to the corporation’s statement, scheduled outages increased to two periods a day, morning and evening, each lasting three hours, after the previous schedule had included a single outage period. This represented a decline in service levels within a short time of the project’s inauguration.
This development came at a time when hopes were pinned on the PetroMasila gas-fired station to help reduce outages and improve the stability of electricity supplies, especially as the season of rising temperatures began and energy consumption increased in residential and commercial areas.
The fault highlighted the importance of the technical readiness of the station’s components, including the gas supply system, pressure units and turbines, as the shutdown of any one of these components can directly affect the total power available to the Wadi Hadramout electricity system.
The General Electricity Corporation apologized to consumers for the disruptions caused by the emergency fault, explaining the technical reasons that led to the increase in outage hours.
This event was one of the first publicly announced operational setbacks following the station’s official opening on April 26, 2018. It revealed that adding new generation capacity alone is not sufficient to ensure electricity stability unless accompanied by continuous operation and maintenance and the availability of fuel.
The event holds particular significance in the timeline of the electricity crisis in Hadramout, as an early indicator of the technical challenges faced in operating the gas-fired station, which later remained a factor affecting the stability of the electricity system in the valley and desert.